Dickson Interchange Stage 1 & 2

Dickson Interchange Stage 1 & 2

Work Type

Civil Construction management Hydraulics

Client

Doma

Description of work

D Group conducted the bulk earthworks for the construction of the DKSN interchange project. The exported material was classified as contaminated due to the presence of heavy metals, which required strict logistics management and extensive stakeholder engagement with neighbouring governmental bodies including Environmental Standards and Worksafe.

Value: $8 million

Duration: 34 Months

Status: Completed

Firing Range Upgrade

Firing Range Upgrade

Work Type

Civil Construction management Hydraulics

Location

Canberra

Client

Sporting Shooters Association of Australia ( SSAA)

Description of work

The project involved 230,00mof material import including civil works, upgrading the firing range stop butt mounds and improving site access to existing firing ranges. Extensive environmental management was required to ensure all contaminants associated with leachate development were encapsulated on site. Continued consulatation with ACT Parks agronomists enabled the management of native grasslands and significant tress. 

Value: $3.6 million 

Duration: 18 Months 

Status:  Completed

Circuit Mark Webber

Circuit Mark Webber

Work Type

Civil Construction management Hydraulics

Location

Pialligo ACT

Client

Circuit Mark Webber

Description of work

D group facilitied the deisgn and upgrade of the Circuit Mark Webber International Kart Track. Site infrastructure including access road and stormwater drainage were upgraded, along with the construction of the new circuit. Works will continue with the track for stage 2. 

Value: $4 million

Duration: 20 Months 

Status: Completed

University of Canberra Training Hospital

Work Type

Civil Hydraulics

Location

Bruce, ACT

Client

Muliplex

Description of work

D Group conducted the bulk earthworks for the construction of the University of Canberra Training Hospital, inclusive of detail excavation, inground hydraulics, foundation of works, slab on groun and landscaping. Roadworks were constructed enabling the permanent access of the site from a major arterial road. 

Value: $11.5 million 

Duration: 7 months 

Status: Completed

Verve Apartments

Work Type

Civil

Location

Newcastle, NSW

Client

Bloc

Description of work

The project consists of construction of 211 residential apartments, over 19 levels with 1 level basement car parking and 3 levels of above ground car parking. Works consisted of: sewer drainage, stormwater drainage, trade waste drainage, siphonic drainage, sanitary stack work, cold water services, hot water services and gas services. 

Value: $3.6 million

Duration: 18 months

Status: Compelted 

Park Avenue Apartments

Park Avenue Apartments

Work Type

Civil

Location

Canberra, ACT

Client

Morris Property Group

Description of work

The Park Avenue Apartments consists of construction of 184 residential apartments from level 4 - 17. This included 3 levels of basement car parking, 4 levels of above ground parking and tenancy provisions. Works consisted of: sewer drainage, stormwater drainage, trade waste drainage, siphonic drainage, sanitary stackwork, hot water services, cold water servoces, gas services and fire services. 

Value: $2.7 million

Duration: 18 Months 

Status: In construction (April 202) 

Palko Apartments

Work Type

Hydraulics

Location

Braddon, ACT

Client

Bloc

Description of work

The project consists of construction of 84 units of 6 levels, including two levels of car parks and 21 tenancies located on the ground floor. Work consisted of: sewer drainage, stormwater drainage, trade waste drainage, sanitary stack work, cold water services, hot water services, gas services and fire services. 

Value: $1.97 million

Duration: 18 Months

Status: Completed

Goodwin Farrer Stage Two

Work Type

Hydraulics

Location

Farrer, ACT

Client

PBS

Description of work

Multi residential/commercial. This project consists of the construction of an aged care facility over three buildings. Building D consisted of 24 apartments with basement car parking, Building E (RACF) consisted of 81 disabled compliant ensuites with support services for staff including doctor and nurses, a commercial kitchen, basement car parking and an office space. Building F consisted of 46 apartments with basement car parking. Work consisted of sewer drainage, stormwater drainage, trade waste drainage, sanitary stack work, cold water services, hot water services, gas services and fire services. 

Value: $4 million

Duration:  24 Months 

Status: Completed

The Capitol Apartments

Work Type

Civil

Location

Civic, ACT

Client

Bloc

Description of work

This project consisted of bulk excavation of a 4 story basement in Canberra City. 

Sapphire Apartments

Work Type

Hydraulics

Location

Kingston, ACT

Client

Bloc

Description of work

This project consisted of the construction of 79 car parks, sewer drainage, storm water drainage, santiary stack work, hot water services, cold water services, gas services and fire services. 

Value: $2 Million

Duration: 12 Months 

Status: Completed

109 Canberra Avenue Apartments

Work Type

Civil Hydraulics

Location

Griffith Act

Client

Bloc

Description of work

This project consisted of bulk and detailed excavation, civil works and hydraulics package. 

The Republic Development

Work Type

Civil Hydraulics

Location

Belconnen, ACT

Client

Geocon

Description of work

The Republic Development included three towers delivered in stages which form part of Canberra's largest mix used development in history. With over 1000 units, a 188 room hotel and a commercial & retail spaces throughout. Excavation was undertaken across three stages totalling 22 000m3 in volume. This development is one of Canberra's largest projects in terms of civil and earthwords. 

Value: $15.5 million

Duration: 26 months 

Status: Completed

 

Marymead Developments

Work Type

Hydraulics

Location

Narrabundah, ACT

Client

Project Coordination

Description of work

This project consists of 84 townhouses, an administration building and a community centre. Works consisted of: sewer drainage, stormwater drainage, trade waste drainage, sanitary stack work, cold water services, hot water services, gas services and fire. 

Value: $3.1 million

Duration:  18 Months 

Status: Completed

Little National Hotel

Work Type

Hydraulics

Location

Barton, ACT

Client

Doma

Description of work

This project consisted of bulk and detail excavation, hydraulics package.

Autoworld Gungahlin

Work Type

Civil Construction management Hydraulics

Location

Gungahlin, ACT

Client

Gungahlin Auto Group/Waves Car Wash

Description of work

This project cosisted of the complete design and purpose built construction. 

Linq Apartments

Work Type

Civil Hydraulics

Location

Belconnen, ACT

Client

Creative Building

Description of work

This project consisted of bulk excavation, detailed excavation, external civil works, hydraulics package and pavements. 

The Apartments

Work Type

Civil Hydraulics

Location

New Acton ACT

Client

Molonglo Group & PBS

Description of work

Bulk excavation, detail excavation, bored piers, shotcrete, design and construction of hydraulics package, directional boring sewer diversions and ACTEW sewer, water & storm water external services.

Realm Precinct

Work Type

Civil Hydraulics

Location

Barton ACT

Client

Doma Group

Description of work

This project consisted of bulk civil earthworks and hydraulics works. It included a 160 unit apartment complex, 80 unit apartment complex with ground floor tendancies and 46 service apartments.

Belconnen Community Health Centre

Work Type

Civil Hydraulics

Location

Belconnen ACT

Client

ACT Government & Hindmarsh

Description of work

Demolish existing carpark facilities; bulk excavation of new underground car parking, including construction of capping beams, bored piers; install drainage, plumbing & gas hydraulics as required.

Kinloch Terraces

Work Type

Civil Hydraulics

Location

Bruce ACT

Client

Doma Group

Description of work

This project consisted of 56 townhouses with 18 unit apartment complex. Bulk excavation, detail excavation, road works, external services abd design & construction of hydraulics package.